Can I demolish my barn? It may seem like a simple question, but the answer depends on multiple factors such as the amount of demolition waste, the presence of asbestos, and the location of your shed. In the Netherlands, clear rules apply to demolition work, even of a relatively small structure such as a barn. These rules are in place to ensure safety, sustainability and spatial planning. In this article we explain what you should legally consider when you want to demolish a barn.

What does the law say, Can I demolish my barn without a permit?

The main rule is no, you should not just demolish your barn. Even with small outbuildings, it is necessary to first check whether there is a notification or permit obligation. The government distinguishes on the basis of two important criteria:

  • How much demolition waste is released?
  • Is there asbestos?

Situations in which you do not need to report:

You may demolish your barn without notice if:

  • Less than 10 m3 of demolition waste is released
  • There is no asbestos in the structure.

If one of these two conditions does not apply, you are obliged to report or even apply for a permit.

When is a notification required?

As soon as 10 m3 or more of demolition waste is released, or if you are going to remove asbestos, you must submit a demolition notification through the Environmental counter. This must be done at least four weeks before the scheduled demolition date.

When is a permit required?

In some situations it goes even further and you need an environmental permit:

  • If your property has a monument status
  • If the barn is part of a protected city or village view
  • If the demolition plans conflict with the zoning plan

In these cases, not only does the notification obligation apply, but you must also formally apply for permission from your municipality.

Zoning and location, what is allowed?

The location of your shed can determine whether you will get permission for the demolition. Especially in the case of buildings in protected areas or on agricultural land, additional rules apply. It is therefore always wise to ask your municipality for the zoning plan.

  • If your barn is located in a protected village, then there is a high probability that a permit will be required.
  • If your barn is on an agricultural plot, you may need to have the zoning changed to “living” if you want to build something new in the same place.

Reasons to demolish your barn

In addition to the question "May I demolish my barn?”, it is also good to reflect on the motivation behind this decision. In practice, we see the following common reasons:

  • Room redesign: think of creating a garden, terrace, swimming pool or extra parking space.
  • Permit-free reconstruction: in some municipalities you can use a demolition bonus scheme, under which you can rebuild the available space (maximum 500 m2 for residential use).
  • Maintenance costs: outdated sheds are often expensive to maintain. Demolition can be more financially attractive than renovation.
  • Asbestos removal: in many old sheds asbestos is still processed. When selling or remodeling, removal is often mandatory.

Whatever your reason, it is important that you continue to operate within the legal framework.

Practical step-by-step plan for demolishing a barn

If you are wondering: how do I handle this correctly?, then the following roadmap will help you on your way:

  1. Check for asbestos
    Have a certified company conduct an asbestos inventory. This usually costs between € 250 and € 500.
  2. Calculate the volume of demolition waste
    Is it 10 m3 or more? Then you are obliged to submit a demolition notice.
  3. Check the zoning plan
    Check with your municipality to see if demolition and any rebuilding are allowed.
  4. Make the notification or request in a timely manner
    • Demolition notification: via the Environmental counter, at least 4 weeks in advance.
    • Environmental permit: includes drawings and construction calculations. The lead time is usually 8 to 14 weeks.
  5. Provide a demolition safety plan
    This is especially important in larger or more complex demolition projects.
  6. Save documentation
    All notifications, reports and permits must be kept for 10 years, for example for a future sale.

Costs to consider

Demolishing a barn involves more than just the physical work. Here is an overview of the possible costs:

PartCost indication
Asbestos inventory€250 – €500
Demolition notificationFree
Environmental permit1-2 – of demolition costs + fees
Architectural drawingsFrom €500

Depending on the complexity, additional costs may arise, for example for constructive adjustments or legal assistance in the event of conflicts.

Have your barn professionally demolished by WijSlopenNu

May I have my shed demolition? As you have read, the answer depends on multiple factors such as waste volume, asbestos and regulations from the zoning plan. So it is important to proceed carefully and legally correctly.

At WijSlopenNu we are happy to help you with this. We not only carry out the demolition work safely and efficiently, but also support in checking permits, requesting demolition notifications, and – if necessary-arranging a asbestos inventory. Do you want to have your barn demolished carefree? Request a free quote today join WijSlopenNu and discover what we can do for you!